
Remember to press for very latest edition
| 12th February 2008: We have now finished the re-timbering job at Alton, with the insertion of the last seven 20 footers. Whilst on site we turned two worn rails. Progress was, however, hampered this week by some very welcome interruptions, as can be seen. |
![]() |
![]() |
![]() |
![]() |
Photos and report (12th February 2008): Dave Tilbury |
Building Dept reports
| 5th February 2008: Fortunately the weekend guys didn't get to do any digging, allowing us to enjoy the full P-Way experience with more digging this week. As can be seen, timbers nearest the camera have been replaced and we are working toward Alton, and the twenty-footers... |
|
![]() |
|
| On the shorter ones we can, in this location, slide out the old and
slide in the new... The screw-spikes are undone over a number of
timbers either side of those to be replaced. The track is jacked up and
the old timber slid out. .
Report and photos (5th February 2008): Dave Tilbury |
![]() |
| And here is the new, with that heap of ballast in the background ready to be put back in place, once the timbers have been packed | |
![]() |
![]() |
28-29th January 2008: On Monday morning we laid a short section of track in the loco yard at Ropley for another tank wagon, then moved on to a bigger project. After loading the Atlas wagon Monday afternoon, on Tuesday started work on replacing the rotten timbers under the point-work at the country end of Alton Station. With 20 plus timbers to be changed you'll understand that there was a lot of digging to be done. Even although we had a small gang this week, we still managed to dig all but the last half dozen. This was a reasonably light-weight job, compared to some we take on, as evidenced by the need to only replace three forks by the end of the day. If we work really hard we can get through many times that. Anyway, we didn't want to finish the job completely, leaving some of the fun for the weekend guys. |
![]() |
![]() |
![]() Report & photos (28-29th January 2008): Dave Tilbury |
| 22 January 2008: On Monday 20 January 2008 we changed a dozen timbers at the far end of Alton yard. The ballast around the timbers to be removed is dug out, spikes are wound out, the rail jacked up and the old timbers slid out under the rail. Piece of cake - or it would be if wood didn't weigh so much. The new are slid back in and once the rail is dropped the timbers are drilled and the chairs spiked down. On the Tuesday we trundled back and forth, picking up ballast from where there was an excess and finishing off the job. Unfortunately I worked so hard that I didn't have time to take pictures.... so here is one at the start of the job, and one at the end. Of course, no one will know that we have been there. No one will notice that the track has ballast where hitherto there was a shovel full of cinders, but come on - look at that 'finished' shot - a nice little path and almost neat shoulders. Whilst we worked on this job, a guy wandered past on the other side of the fence, presumably checking the line on the 'big' railway. He looked a little perplexed and so we exchanged pleasantries with him. "Yes", we said, "We do this as volunteers". "Oh", he said, "I thought you looked too bloody old for a proper P-way gang". No one mentioned Portsmouth track relaying or the delays across the country after the Christmas maintenance by the "young professionals...." |
![]() |
![]() |
For those with an interest in Wickham vehicles, our other trolley is
currently undergoing repairs. The gearbox, clutch and flywheel are out
and we are looking for a new starter ring, clutch slave and master
cylinders. All this is being carried out on a draughty siding in
Medstead, but you'll not hear us complain. Report and photos (20th January 2008): Dave Tilbury
|
| 14th December 2007: Following the excitement at Ropley P-Way matters have returned to the mundane - gathering scrap, mending fences, drinking tea and generally sheltering from the rain. The good news is, we have a new man on the mid-week gang and he is under 70 and fit, giving the rest of us the luxury of a little more 'shovel leaning' time. Welcome John. Photos and report (14th December 2007): Dave Tilbury
|
|
![]() |
![]() |
![]() |
![]() |
Re-aligning the track
and installing new points, track-circuits and signalling past the Up
starter at Ropley station
|
||||||||||
| 14th November 2007: The line is now laid and ballasted and will be allowed to settle before fine tuning. To extend the points rodding, new trestles and roller frames were being sunk. The bell-crank for the yard points was mounted but not connected up by the time the light went. Photos (14th November 2007): Tony Wood
![]() |
![]() |
|||||||||
November 2007:
Movie: P-Way gang from M4M arrive at Ropley by Wickham trolley (12.3MB, mp4, November 2007): Dave Tilbury
Movie: Early stages (16.8MB, mp4, November 2007): Dave Tilbury
Movie: Lifting the track (13MB, mp4, November 2007): Dave Tilbury
Movie: Replacing the track (15½MB, mp4, November 2007): Dave Tilbury
Movie: Adding the stone (8.3MB, mp4, November 2007): Dave Tilbury
Movie: Keystone Cops version (15¼MB, mp4, November 2007): Dave Tilbury
| 12th
November 2007: Another fine day saw the track completed. Pat Butler's team had got the points working smoothly and precisely, but rodding is yet to be run to the signalbox. The yellow machine shown being used by Paul Hawley drills twin holes for track circuit continuity links across the rail-joints. Next job looks to be the ballasting ready for the jacking and packing. |
||||
|
Minutes of MHR Ltd October 2007 Board Meeting includes:
"It was noted that the HMRI complimented the railway on its track."
|
![]() |
![]() |
![]() |
|
![]() Click thumbnails |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Cameo shots of 12th Nov work : Movie (6.2MB) Photos and movie (12th November 2007): Tony Wood |
|
| |
||||
| 7th November 2007: |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
| Good weather and good progress with
the
current Ropley job: I hope the photos tell the story. I took the stepped fishplates one because the question was asked: "How do we align the top surface of the rails when there is a step at the rail-joint?" Today's work - The Movie (15MB) Photos
and movie (all 7th November 2007): Tony Wood
|
||||
| 19th July 2007: Replacement for the old P-Way blue van, ex-BT but with a brand-new tipper body Photo
(Ropley, 19th July 2007): Tony Wood
|
![]() |
![]() |
17th July 2007:
![]() |
| With most of the fencing issues
dealt with, the mid-week P-Way gang are
back to the more usual tasks of jackin' n' packin'. We have also spent
a couple of days clearing vegetation down at Butts Junction and
recovering a significant amount of metalwork that we cut up, craned out
and shipped away to the scrap merchant. The replacement points for the north end of Ropley loop have been prefabricated and broken down ready for shipping to the site, some time this coming winter. There is no shortage of maintenance tasks to be dealt with and the wet weather has added a couple of minor land slips to the list of things to be done. When walking the track this week it was apparent, from washed debris and flattened grass, just how much water had poured down through the cuttings. In places the ballast must have been submerged. We have also started to address the mess at Miller's Crossing, where unsightly bags of spoil have have been dumped. We will need to return at some stage with the Atlas wagon to shift the remaining bags and conceal with a layer of soil. Hopefully next year this eyesore will be invisible. |
|
![]() |
Our resident photographer has left
his vantage point on several
occasions and applied his winning ways to the serious matter of
scrounging strawberries & cream for the gang. With a daily
service
through the 'summer' our working day is dictated by the train timetable
- and one of those trains has a buffet... Still, all work and no play,
etc. Our safe working practices invariably make for an incident free work environment, with little in the way of excitement to comment on. That said, the recent ban on smoking in the work-place has caused some friction. One of our number smokes and we have pointed out that the track is our place of work and that he should desist from his foul habit. Quoting from the statutes has thus far only elicited a monosyllabic response. Now, if only we could apply the 'No Smoking' ethic to the Wickham. Report
and photos (17th July 2007): Dave Tilbury
|
![]() |
|
| 12th
June 2007: Today we started work in earnest on the new track layout for the London end of Ropley station. First two rails are laid out on some convenient and flat place, in roughly the right place. These are then jacked up and rested on blocks whilst the timbers are slid into position. With one rail loosely screwed down the other is positioned accurately with square and gauge before fixing. Once the panel is complete it is numbered, marked and stripped down for shipping to site so that what is now a numbered kit can more swiftly be assembled when the running line is taken out. To further speed the job, we have two of these little machines for boring holes for the fish-plate bolts. These can be operated by one man and cut a hole in around 30 seconds. The old boring machine took four guys to lift and did not cut as quickly. Sadly, the road-railer (seen behind at right) was inoperable due to a fault, so ALL the lifting was 'handraulic' - but you'll not hear us complain..... |
![]() |
![]() |
Report and photos (12th June 2007): Dave Tilbury |
P/Way page archives: 2000 - 2002 & 2002 - 2005 & 2007 - 2008 & LATEST
Very Latest News from the Loco Shed
Index of Archived Loco Shed Pages
LSWR Type 1 Signalboxes on MHR
Very Latest News from Mid-Hants Railway